A bulk water station retrofit replaces the old payment and control gear and keeps the piping, meters and valves that still earn their place.
By Pro-Tech Systems Group, Akron, Ohio
Key takeaways
A bulk water station retrofit swaps the aging payment and control equipment and keeps the parts of the station that still work. Our panel can work with an existing water supply line, so your piping can often stay in place. Meters, valves and wiring get a quick review before you set the scope.
We recently heard from an owner of a 20-year-old, privately owned station that serves a few fleets and many rural families hauling water to their homes and ranches. The station has metered supply lines and meters at its two dispensing points, and it sells water by measured volume. The controller was adapted from a car wash system that is no longer supported. The owner wants to keep selling by volume and add tap-to-pay and mobile wallets next to card swipes.
That is a common starting point. The job is to sort the station into three piles: keep, replace and check. The rest of this post shows you how.
If you are still weighing the decision itself, read why cities switch from coin-op to cashless. This post is the practical how-to that follows that decision. For the panel itself, see the bulk water station product page.
Most owners come to us with one of these four problems. Writing yours down makes the site review faster for your engineer or contractor.
Note the make and model, and keep any manuals or wiring drawings you have. A controller adapted from another application, like a car wash, often has no parts or support left. That alone is reason enough to plan the replacement.
List the components your maintenance crew can no longer repair or replace. Separate the faults that stop sales from the ones that only affect a display or a card reader. That tells you where the real boundary of the job sits.
Write down what customers use today and what they are asking for. Customers now expect chip cards, tap-to-pay and mobile wallets. Treat prepaid balances, account cards and bank cards as three separate lines on your list.
Record any trouble with delivered quantity or supply shutoff. Have your contractor sort controller faults from meter, wiring or valve faults. A new panel fixes the controls, and a worn valve still needs its own repair.
Before you request a quote for a bulk water station retrofit, walk the station with your maintenance lead or contractor. Use this table as your survey guide.
| Station Component | Direction | What to Look At |
|---|---|---|
| Water supply line | Keep, if sound | The panel can work with an existing supply line. Check its condition and connections. Line pressure sets the fill speed. |
| Building and panel location | Keep, if suitable | The panel can mount indoors or outdoors. A building or enclosure around the station is your choice and is not standard. |
| Backflow prevention | Check | Anti-siphon devices keep doing their job. Have your plumber confirm they suit the new installation and your state rules. |
| Dispensing equipment | Check | Look at condition, connections and how a fill starts and ends. Much of it may be able to stay. |
| Flow meter | Check | We bill with a meter certified legal for trade. Confirm your existing meter’s status and that it gives a usable quantity signal. |
| Shutoff valve and actuator | Check or replace | Verify condition, electrical needs and on/off operation. Decide what the valve should do if power is lost. |
| Payment equipment | Replace | Chip cards, tap-to-pay, mobile wallets and owner-issued RFID cards are supported. Card dispensers and legacy readers get reviewed with your account plan. |
| Control panel | Replace | The enclosure is usually National Electrical Manufacturers Association (NEMA) 4X. Every panel includes an internal heater and fan as standard. |
Pro-Tech Systems Group is an industrial automation and control system integrator based in Akron, Ohio. We design and build control panels and program programmable logic controller (PLC), human-machine interface (HMI) and supervisory control and data acquisition (SCADA) systems. Our control systems work covers the panel and the programming behind it.
The water sequence is simple. After a customer pays, the panel turns the supply on. It measures what is delivered and turns the supply off when the paid amount has been delivered.
The panel does not control or regulate flow. The pressure in the feed line dictates how fast a customer fills.
For water, we use a flow meter that is certified legal for trade, so the station bills by measured volume. NIST Handbook 44 holds the US specifications for commercial weighing and measuring devices. Your local weights and measures office can tell you how it applies to your station.
If you want to keep an existing meter, send us the model, certification details and output information. We need to confirm it gives the panel a clean quantity signal for billing.
Customers can pay several ways:
Owner-issued cards suit regular customers like fleets and haulers. If you run a prepaid system today, decide how current balances will move over before you tell customers about the change. That one decision saves a lot of phone calls later.
For card security, the PCI Security Standards Council publishes the card payment security standards. Your payment provider and project team can confirm who handles which part.
The same control system can be used for ice, grain, candy and other products sold by a measurable quantity, with the program adjusted for each application. Water is the application in service today.
A good survey records what is installed and what you want the new system to do. Photos and documents save a lot of back and forth.
Treat equipment ordering and field installation as two tracks. The panel is built while you line up your contractor.
01
Send Pro-Tech your survey, equipment records, payment wishes and known faults. Mark what you need and what would be nice to have. Add your operating concerns so the review covers more than a parts list.
02
Settle equipment reuse, mounting, electrical connections, metering and supply shutoff before you approve the design. Agreeing on scope here keeps surprises out of installation day.
03
Lead time is 14 to 18 weeks including engineering submittals. The panel build alone is about 8 weeks. Use that window to book your electrician and plumber and to plan customer notices.
04
Settle how accounts and prepaid balances transfer before you issue new cards. Your electrician and plumber, or your contractor, handle installation. Pro-Tech provides the installation documentation.
05
Agree on startup checks with your project team. Test each payment method, the measured delivery and the supply shutoff at every dispensing point. Then open the station to customers.
Remote monitoring is a separate conversation from payment and shutoff. If you want it, our network telemetry and SCADA system pages explain the related work. Decide who needs the data and what they need to see.
Pro-Tech panels are made in Akron, Ohio. Buy American documentation is available on request, which matters to buyers using federal funds such as State Revolving Fund money.
The EPA publishes the Build America, Buy America requirements for Clean Water State Revolving Fund projects. Your funding administrator can confirm what applies to your project and what records you need.
Prices come with a quote, because they depend on the instrumentation you need and your installation site. For wider planning, the bulk water fill stations buyer’s guide covers the municipal side.
Owners, engineers and contractors can call 330-773-9828 to talk through the station and request a quote. You can also use the contact page. We will help you plan your bulk water station retrofit.
Pro-Tech Systems Group builds payment and control panels in Akron, Ohio. Call 330-773-9828 or tell us about your station.
Often, yes. Pro-Tech’s payment panel can work with an existing water supply line. Your contractor and plumber should check the condition of piping, valves and backflow devices, and confirm they meet your state rules, before the scope is set.
No. The panel turns the supply on after payment and off when the paid amount has been delivered. The pressure in the feed line dictates the fill speed.
Pro-Tech uses a flow meter certified legal for trade for water, so the station can bill by measured volume. If you want to reuse an existing meter, send its model and certification details so we can confirm it works with the new panel.
That depends on your current card system, so plan it early. Pro-Tech supports chip cards, tap-to-pay, mobile wallets and RFID cards issued by the station owner. Decide how existing balances and accounts will transfer before announcing the change.
Lead time is 14 to 18 weeks including engineering submittals, and the panel build alone is about 8 weeks. The customer or the customer’s contractor, such as an electrician and plumber, installs the panel. Pro-Tech provides installation documentation.
No. The panel can be mounted indoors or outdoors, and the enclosure is usually NEMA 4X. Every panel includes an internal heater and fan as standard. Building an enclosure or a building around the station is the owner’s choice.